Brandy redux -> RE: Yearly view (8/30/2012 5:23:20 PM)
|
Hi Brenda, After you select the Year view, you would do this: 1. If your project is displayed with more than one page, scroll to the left - to the first page of the Year view. 2. Right click on the events in the center of the first page of the Year view (DO NOT right click on the small calendars), then select 'Properties' from the menu that drops down. 3. When the 'Layout Object Properties' window opens, click on the 'Miscellaneous' tab. 4. On the Miscellaneous tab, change the date in the 'Start Date: month/year' box. 5. Make sure the desired number of months is selected in the 'Number of Months' box. 6. Click on the 'OK' button to return to the workspace.
|
|
|
|