Hi sorrentino, You can do it if you use the Multi-Week view. To switch to a Multi-Week view, click on the down arrow in the bottom toolbar at the top of the design screen, then select Multi-Week in the list that drops down. To set the calendar for Aug 28th through Oct 1st, right click on an empty day cell then select Properties from the menu that drops down. When the Layout Object Properties window opens, click on the Multi-Week Properties tab. On the Multi-Week Properties tab, click on the button next to the Start Date box, then select Aug 28 on the calendar. Then, change the Number of Weeks to 5. Then, click on OK to return to the calendar.