		 Hi waymangoodhope,      To shade an entire month, you would do this:      1.  Right click on an empty day cell, then select 'Properties' from the menu that drops down.      2.  When the 'Layout Object Properties' window opens, click on the down arrow next to the 'Set Properties of' box, then select 'Cell' in the list that drops down.      3.  Select the desired shading options, then click on 'OK' to return to the calendar.      It is very important, however, to keep in mind that when you make a change to one month, that change is automatically applied to all months.  So, it is not possible to shade alternating months. 
			
			
  < Message edited by Brandy redux -- 6/5/2011 11:58:17 AM  >					
			
			 